Engine Assembly Line Optimization

Project Scope


  • Unable to match Line Production v/s Line Capacity

  • Identify bottlenecks in the engine assembly line

  • Simulate both existing model and new model

  • Provide solutions to eliminate bottlenecks


Business Challenges


  • Line capacity – 140 engines per shift

  • Currently production 75 engines per shift

  • No visibility on number of resources and machine / space utilizations


ARi’s Solutions


  • Identified stations above TAKT (above 3 mins 25 seconds)

  • Balanced cycle time and operator time in each station under TAKT


ARi’s Value Proposition

Production increases to meet line capacity at different scenarios, bottlenecks eliminated to achieve 140 engines per shift.


Download
Case Study

Download Case Study

Case Studies

Related

Welding Fixture Design for Truck Body

2025

Welding Fixture Design for OHT’S

2025

Truck Body Welding Line Layout Development

2025

Reverse Engineering – Warm Forge Die Set

2025

Design of Lifting Tackles with Turnover Scope

2025

Design of Lifting Tackles for Simple Components

2025

Design of Lifting Tackles for Large Products

2025

Design of Lifting Tackles for Complex Components

2025

https://www.arigs.com/wp-content/uploads/2025/11/Engine-Assembly-Line-Optimization.pdf